CARRBORO, N.C. -- About 4,000 square feet of sidewalks around Carrboro are being repaired in a project underway now through the end of January 2022.
Included in the $75,000 maintenance and repair project are sidewalks, wheelchair ramps, and curb and gutter work. The work consists of replacing damaged sections of sidewalk including trip hazards and upgrading curb ramps to current ADA standards.
Sidewalk repairs will be made at the following locations:
- Atterbury, N. Camellia, W. Winmore, S. Camellia, Kiley, Sharp, Jewell, Lucas, Della, Stratford, Tramore, Ellsworth, Autumn, Farm House, Sunset Creek, Rockgarden, Cates Farm, Bel Arbor, Long Meadows, Legends, N. Fields, Shadow Ridge, Hogan Woods, Lake Ridge, E. Main, and Martin Luther King Jr. Park.
A concrete saw and jack hammer will be used for demolition so residents should expect short durations of noise associated with the demo.
For more information, contact the Carrboro Public Works Department at 919-918-7425 or PWorks@townofcarrboro.org
###