CARRBORO, NC -- Construction continues to progress on The 203 S. Greensboro Street Project in Carrboro.
Work performed in last 30 days:
- Installation of pavers at terraces
- Installation of coping on roof parapets
- Signage installed in parking deck
- Installation of restroom fixtures
- Carpet installed on all levels
- Ceiling tiles, ceiling baffles, and cabinetry nearly complete
- Wall finishes and final painting in process
Work upcoming in next 30 days:
- Continuation of sidewalk, curb and gutters
- Installation of landscape lighting and irrigation
- Installation of exterior benches
- Install handrail and plant material for terraces
- Audio visual systems will begin installation
- Fire alarm system to be completed and tested
Utility work, site work, and traffic impacts:
Installation of sidewalks, curbs and gutters around the site is in progress and will continue. Periodic road closures of East Braxton Foushee, Maple Avenue Extension, and Roberson Street will continue as needed to accommodate. Road closures will occur during the day and reopen each evening.
Completion of project:
We look forward to welcoming everyone at the new public center in Carrboro that will be both a library and civic building. After construction is completed, it will take some time for services to move in and become operational. The grand opening date will be announced broadly when it is confirmed. This will be set in coordination between the Town of Carrboro and Orange County, following the completion of construction, and the move-in of furniture and library materials.
Background:
The $42 million development will be the future home of the Orange County Southern Branch Library. The facility will also provide a permanent home for the Orange County Skills Development Center; Carrboro Recreation, Parks and Cultural Resources Department; WCOM Radio; and performance/multipurpose uses. The 203 Project will provide opportunities for education, art, and community connection.